14 Production
← Technical Guide

Chapter 14

Production

Work orders, machine capacity and shift calendar, delivery date risk, OEE and the six big losses, factory dashboard and work order cost: what each screen measures, where the data comes from and who sees it.

Overview

The Production module reads the shop floor's plan (work orders and operations), the machines' shift calendar and the events recorded on the shop floor (shift closing, stoppage, production confirmation, constraint declaration) on the same records. The menu has seven screens: Factory Dashboard, Work Orders, Capacity and Load, Shift Calendar, Delivery Date Risk, OEE and Constraint, and Cost.

GateKeyWhat it unlocks
Licensemanufacturing_moduleAll screens of the module. Without a license, you are redirected to the features page with an upgrade link.
View permissionmanufacturing.viewReading all screens. Without the permission, the module pages do not open.
Manage permissionmanufacturing.manageEntering work orders, operations and shop-floor events, changing step status, and entering consumption on the cost screen.
View costsmanufacturing.cost.revealThe amounts on the cost screens. Without the permission, the amounts are not read on the server.
Manage costsmanufacturing.cost.manageAdding entries to the machine rate, unit amount and scrap allowance ledgers.
View salarieshr.salary.viewSeeing the labor component and labor rates, together with the permission to see costs.

Factory dashboard

A one-page view of the shop floor for the day or week you select. With the date navigator you move to the previous or next window, go to a date, or return to today; the window can be a single day or a week. The strip at the top shows the number of machines in service, OEE, good/scrap quantity, total stoppage, the bottleneck and the number of anomalies. Below it are four sections: flow map, machines, bottleneck and anomaly feed.

  • Flow map: connects two consecutive steps of the same work order on different machines with a line (cancelled steps excluded). The layout is set up automatically; it is not a floor plan. If there is no route link between machines, the map is not drawn and says so.
  • Machine cards carry a status chip; order of priority: Bottleneck, Has downtime record, Has production record, Outside calendar and No record. You can filter by status, machine and loss class.
  • On the machine card, under the «OEE (window)» row, the Availability, Performance and Quality ratios appear as bars; the three bars together open the machine's page on the OEE and Constraint screen. The bar of a ratio that cannot be measured stays empty and says «not measurable»; the reason is in the row's tooltip. If the window is entirely after today, it says «has not come yet». Neither is drawn like a zero. A ratio whose displayed percentage exceeds 100 is additionally labeled «over 100%»; this can be seen in the Performance ratio when the standard time was entered generously. The panel that opens when a machine is selected on the map shows the same bars.
  • The operator figures on the map are people who recorded shop-floor events in the last 7 days, and they are shown not by name but by a sequence number such as «Operator 1», «Operator 2».
  • The bottleneck is the machine with the highest ratio of planned load to measured capacity, and whose ratio goes above 100%; if no machine exceeds it, the screen states that there is no bottleneck and shows the most loaded machine. The ratio is the same as the calculation on the Capacity and Load screen.
AnomalySeverity
Breakdown stophigh
Other stopmedium
Confirmation with scrapmedium
Constraint declarationinfo
Capacity overrunhigh
Load without capacitymedium
Due-date riskhigh

At the start of the anomaly feed, before the filter chips, there is the «Standing out in this window» box. The box shows at most three of the window's anomalies up to today; the number in the heading is the number of listed rows. The order is severity, then day (newest to oldest), then magnitude (minutes or scrap quantity); in a complete tie, the record key fixes the order. The type, machine and loss filters do not change this box; they apply only to the full list below. The rows are the same as in the list below and lead to the relevant screen: the Breakdown stoppage, Other stoppage, Confirmation with scrap and Constraint declaration rows go to the machine's page for that day on the OEE and Constraint screen; the Capacity overrun and Load without capacity rows go to the Capacity and Load screen; the Delivery date risk rows go to the at-risk list on the Delivery Date Risk screen.

  • Only plan warnings can fall on a future day (Capacity overrun, Load without capacity and Delivery date risk); these do not enter the box, and their count is written in the «Future days (plan)» row.
  • Anomalies that cannot be linked to a machine are counted in the «No machine link» row.
  • These two rows are visible only when the count is greater than zero.
  • If all anomalies in the window are on future days, the box says so instead of showing a list; if there are no anomalies at all in the window, the box is not drawn.

Work orders

Lists open work orders and their delivery dates (open = planned + in production). The cards show the number of open work orders, the late ones, the average delivery date slip (actual finish − planned finish) and the actual cost. «Late» is measured not against the promise made to the customer but against production's own planned finish. The filter chips separate open, late, completed and work orders with no cost entered; late and no-cost-entered are subsets of the open ones, completed is a separate list and shows at most 200 records (if the window fills up, it says so).

ColumnMeaning
Work order · Product · QuantityThe work order's number, product code and quantity.
Planned finish · Delivery datePlanned finish and the delivery date verdict.
StatusPlanned, In production, Completed and Cancelled.
BatchBatch / serial number.

If you have the manufacturing.manage permission, you can enter a work order: number, product code, quantity and unit, status, planned and actual finish, batch / serial number and description. The cost fields are not on this form. Clicking a work order opens its details: the delivery date verdict and steps; you change a step's status with the manage permission. For a work order whose steps have not been entered, or all of whose steps have been cancelled, the screen does not say «not at risk»; it treats the verdict as not measurable; steps are entered on the Capacity and Load screen. For a work order that is not open, the delivery date verdict is not shown.

Capacity and load

Shows the machine × day utilization grid for the selected week; you can move to the previous and next week. Each cell is the ratio of planned load to measured capacity. Load is setup and processing time; capacity is the net minutes of the shift bands. Stoppages, scrap and labor assignment do not enter the capacity calculation; utilization is not a measure of efficiency. Cancelled operations do not count toward load; completed ones do.

  • Cards: the number of machine·days exceeding capacity, the load falling on days without capacity, and the number of open work orders with no operations at all (load not measured). Below each card is the relevant list; the rows go to the machine's OEE ledger for that day or to the work order detail.
  • No shift defined: define a shift band for that day or move the job to a working day.
  • Machine out of service: move the job to a machine that is in service — no shift is written for a retired machine.
  • If a machine-day's capacity exceeds the minutes in a day, the screen shows a scope warning: night shifts are totaled on the day they start.

With the manufacturing.manage permission, you enter operations for a work order through the «+ Add operation» form: work order, machine, sequence no., step name, planned day, quantity on that day, setup time, processing time per unit, status and description. For a step spread over several days, a separate row is entered for each day. The load minutes are calculated in the database: setup + (processing per unit × quantity, rounded up). The form requires at least one machine and one work order.

Shift calendar

Shows each machine's shift bands for the selected week, read-only. The cards count the machines in service, the machines with no calendar entered this week and the inconsistent records (a band valid on a day when the machine is out of service); the same three groups are filter chips. The table shows the machine, which days of the week are covered by a band, the bands and the machine's status. Bands that overlap the week are shown; those outside the window are not shown.

Delivery date risk

Shows, as of a verdict day, whether the schedules of open work orders fit within machine capacity. The delivery date is the work order's planned finish. Each open work order falls into exactly one group: Delivery date at risk, Data defective and Fits. The cards count these three groups and are also used as filter chips. A work order can have more than one finding; the distribution of findings therefore overlaps, and the number of «work orders for which a verdict can be given» is written separately.

FindingClusterMeaning
Not scheduledDefective datahas no operation entering the calculation (none entered or all cancelled); load and finish cannot be measured
Scheduled lateDue date at riskthe last day of the schedule exceeds the delivery date
Relies on a full dayDue date at riskthe dates hold, but at least one operation day is over capacity or that day's capacity cannot be measured
Under-scheduledDefective datathe scheduled quantity is below the work order quantity
Over-scheduledDefective datathe scheduled quantity is above the work order quantity
FitsFitsfits the machine capacity; this does not mean «finishes on time»

Rows lead to the work order details; risky days link to that machine's single-day OEE page. If there is no work order, no open work order (completed and cancelled ones are not counted as risk), or no operation has been entered, the screen says so separately for each case; operations are entered on the Capacity and Load screen.

OEE and constraint

Shows the machine fleet's availability (A), performance (P), quality (Q) and OEE (A×P×Q) ratios over the selected date range (default last 14 days). The color of the cards is only a display tone, not a verdict: 85% for A and P, 97% for Q, 65% for OEE.

  • A = (net − downtime) / net; net is the net time entered at shift close.
  • P = confirmed quantity × operation standard / (net − downtime). P is not clipped: a value above 100% shows that the operation standard is wrong.
  • Q = good / (good + scrap).
  • OEE is multiplied only on a machine where all three of A, P and Q are measured. Cancelled records and the records they reversed do not enter the calculation. Downtime falling on a day without a close does not enter A, and the standard of the confirmation does not enter P; if there is no shift close, only Q can be measured.
  • If downtimes on a machine-day exceed the closing net time, that machine's A is not measured; in that case the fleet A is not measured either, and OEE is not multiplied.
Six big lossesAxis
BreakdownA
Setup and adjustmentA
Minor stopP
Speed loss (derived)P
Start-up scrapQ
Production scrapQ

The six big losses section groups these classes by axis (A · Availability, P · Performance, Q · Quality) and shows each as a bar in the fleet's total minutes; the largest is marked «largest loss». Scrap classes are converted to minutes by scrap quantity × operation standard. Speed loss does not come from a record; it is derived from the difference between the time worked and the standard. If the fleet's P has not been measured, the speed loss row says «not measurable» and states the reason; no bar is drawn, it does not count as the largest loss, and the total does not include it («excluding speed loss»). Clicking a class filters the machine table to the machines that produce that loss; clicking again removes the filter. A class that produces no minutes cannot be clicked. The filter does not change the cards above or this section.

The Constraint section shows the constraint machine (declared or derived from the plan), the time lost at the constraint, the constraint OEE and the protective capacity on non-constraint machines; if the declaration and the plan conflict, it says so. If the constraint machine's P has not been measured, the time lost at the constraint does not include speed loss, and the card states this together with the reason. The machine table gives each machine's closing, net and stoppage minutes, good/scrap quantity, OEE and lost minutes; for a machine whose P is not measured, the lost minutes do not include speed loss. Clicking a machine opens the machine page: a day-by-day table, the machine's six losses, the operations loading it and the event ledger. With the manufacturing.manage permission, you enter shop-floor events from here: Close shift, Enter stoppage, Enter production confirmation, Declare constraint and Cancel a record (reversal entry). Without the permission, the page is read-only. A window with no records does not mean the factory has stopped; the screen states this separately.

Cost

Compares the unit cost per product of completed work orders. The screen opens with manufacturing.view, while the amounts require the manufacturing.cost.reveal permission; without it, the data layer does not read cost at all, and the screen tells you to request the permission under Settings → Roles. The labor component additionally requires hr.salary.view.

Unit cost = actual cost ÷ good quantity of the valid confirmations at the last step of the route; cancelled confirmations are deducted. The product table shows the number of completed and measurable work orders, the excluded ones and the reason, the lowest and highest unit cost, and the difference per piece. Exclusion reasons: the confirmation total exceeds the quantity, partial confirmation (missing step), good quantity 0 at the last step, actual cost not entered and no route, the last step cannot be determined.

  • Product page: the Material, Labor, Energy, Consumables, Subcontracting, Depreciation, Overhead and Setup components; actual cost (a total entered externally, with no breakdown), the amount per good unit and per planned unit, catalog and route standard, and the bridge against the route.
  • Cost bridge: breaks down the difference between two work orders, or between a work order and the standard, term by term. Without the labor (salary) permission, the difference is not broken down into terms.
  • Work order breakdown: step durations, the consumption ledger and the distribution of the closing time (setup, run, unabsorbed fixed cost). With the manufacturing.manage permission you enter material, consumable and subcontract consumption, mark the entry as finished, or make a reversal entry.
  • Rates and standards: machine rates (per minute), material unit amounts, expected scrap shares, and a rate suggestion derived from finance's realized expense items. Adding a record requires manufacturing.cost.manage; records are not deleted, a new date opens a new version. The suggestion is not written to the ledger by itself; salary items are not read.